CLIENT: Mavi Yeşil Enerji Ltd. Şti. / ACAR İNŞAAT
SCOPE: Preparation of Bankable Feasibility Report
DATE: 2017
PROGRESS: COMPLETED
PROJECT INFO:
- Total Installed Capacity: 4.625 MW
- 3 cascade diversion type hydropower facilities
- Design discharge: 0.95 m³/s, 1.50 m³/s, 1.80 m³/s
- Gross head: 448.33 m total
- Location: Imereti/GEORGIA