SCOPE:

 

  • Hydraulic and structural design of powerhouse related to Replacement of turbines,
  • Hydraulic review of available facilities for improvement.

 

CONTRACT DATE: 2016

 

PROGRESS:

  • Final design completed and approved by General Directorate of Turkish Electromechanics Industry.
  • Detailed design is completed. Construction and commissioning completed.
  • The facility has started commercial operation with the brand new E/M equipment.

 

PROJECT INFO:

  • Located in Amasya/ Turkey,
  • Installed capacity is 10 MWm/1.07 MWe,
  • Gross head: 129.0 m
  • Design discharge: 1.00 m³/s
Test

Form Gönderimi

Tamam

Contact
Hidroyapı Proje Mühendislik Danışmanlık LTD. ŞTİ.
Kabil Caddesi,1337-2. Sokak, No:2/12, Öveçler / ANKARA / TURKEY
0 312 479 16 30
0 312 479 16 31 info@hidroyapi.com
© 2025 Hidroyapi.com.| All rights reserved.